Yesterday we had a very exciting meeting down at the Skate Park, Lesley, Cllr Lyn Harris and met the FOSP down there and had a good look round and update from Daryl.
Upcoming progress plan:
Please see updated plan for coming weeks. Of course this can be subject to change as there are quite a few moving parts. As discussed, we are now becoming more at the mercy of the weather, though we will do everything in our power to work around these challenges. Our current plan:
7-9th February – Pour remaining elements, begin pouring flat slabs
12-16th February – Set pool coping in stair feature corner, install rebar in flat slabs (potential flat slab pour)
19th – 23rd February – Pour remaining floor slabs
26th – 29th February – (back up floor slab pouring in inclement weather) detail work, snagging, regrading of temporary access paths
4th – 8th March – handover for final top soiling works